Question: Select the correct answers. If all resources have capacity utilization ratios less than 1 , the system constraint ( s ) is ( are )

Select the correct answers.
If all resources have capacity utilization ratios less than 1, the system
constraint(s) is(are) the
If at least one resource has a capacity utilization ratio greater than 1, the
system constraint(s) is(are) the
If the resource with the highest capacity utilization ratio has a capacity
utilization ratio equal to 1, the system constraint(s) is(are) the
 Select the correct answers. If all resources have capacity utilization ratios