Question: Select the correct statement about risk identification. Question 5 options: It is the second step of risk management processes that lists all the possible risk
Select the correct statement about risk identification.
Question options:
It is the second step of risk management processes that lists all the possible risk events that may affect the project's objectives and documents their characteristics
The main output of the risk identification process is what is known as "Technical Risk"
Estimates, assumptions, and constraints fall under technical risks
This process should be done only at the beginning of the project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
