Question: Select the fact(s) below that would go under a heading Work Completed in the Progress Report for the above noted renovation project. Follow the guidelines

Select the fact(s) below that would go under a heading "Work Completed" in the Progress Report for the above noted renovation project. Follow the guidelines reviewed in class.*

1 point

Work is progressing on schedule

The resurfacing of all wood floors, replacement of drywall, and installation of lighting systems will take place August 5 to August 18.

There should be no difficulties in finishing all work by the scheduled completion date.

Original quote you gave your client was $475,000 to complete the entire job

Costs of materials are coming in higher than you quoted her.

Replacement of heating and air conditioning system is in the preliminary stages

Materials costs to date are $90,500

You said you would be finished by August 20

The remainder of the labour costs you estimate is $73,000

As of July 6, all plumbing work has been done, and the circuit breaker panels, meters, service outlets, and all sub-flooring have been installed

Work is being done faster than expected so labour costs will probably end up lower.

Labour costs to date are $217,000

The remainder of the materials costs you estimate is $85,000

As a result, costs overall will not be higher than expected.

The upgrading of the central office and meeting room has been scheduled for completion from July 15 to August 4.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!