Question: Select the option that describes reserve estimating. a . ) Involves identifying the money needed to cover project changes b . ) Uses comparisons to
Select the option that describes reserve estimating.
a
Involves identifying the money needed to cover project changes
b
Uses comparisons to similar projects to guide estimates
c
Involves setting a cost or value for each activity
d
Uses real costs for a project and does not allow for any variations