Question: select three benefits of using CPM construction scheduling software like Microsoft Project or Primavera P 6 . A . it allows you to see your

select three benefits of using CPM construction scheduling software like Microsoft Project or Primavera P6.
A. it allows you to see your sceduling input in severzl different views
B. it automatically generates a work breakdown structure from the Gantt chart
C. it simplifies the process of updating the schedule
D. it clearly surfaces parallel activited on the project
E. it identifies long lead items without user input
F. it helps facilitate pull planning in the field