Question: Senior Field Engineer, 4 5 weeks. Superintendent, Maximum, 5 0 weeks. Clerk, 5 0 weeks. The work will be performed in Miami, Florida. For RSMeans

Senior Field Engineer, 45 weeks.
Superintendent, Maximum, 50 weeks.
Clerk, 50 weeks.
The work will be performed in Miami, Florida. For RSMeans parameters use:
Type: Unit
Labor Type: Open Shop
Release: Year 2024 Quarter 2
Using RSMeans Data, estimate the total bare Overhead costs related to worksite personnel and insurance for a small commercial new construction project based on the schedule itemized below.
Senior Field Engineer, 45 weeks.
Superintendent, Maximum, 50 weeks.
Clerk, 50 weeks.
The work will be performed in Miami, Florida. For RSMeans parameters use:
Type: Unit
Labor Type: Open Shop
Release: Year 2024 Quarter 2
The total bare overhead costs are $379,505.00
The total bare overhead costs are $179,505.00
The total bare overhead costs are $242,200.00
The total bare overhead costs are $119,700.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!