Question: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. ( i . e .
Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. ie When a job is complete on its first workstation, it must wait hour move time before it begins on the next station
Example of Move Time
Machine A
Machine B
Sequence the jobs in priority order Assume hr work days.
Job Work CenterMachine Hours Due Date Days
A B C
C A
B A C
C A B
a What is the total makespan?
b How much machine idle time is there?
c When is each job delivered compared with its due date?
d How much idle time waiting time is there for each job?
e Devise a better job sequence for processing.
Problem
In problem assume there are two machines of type A two of type B and two of type C
a Prepare a finite capacity schedule
b How does your FCS compare to the performance of the Gantt chart in problem
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock