Question: Sequence the jobs shown by using a Gantt chart. Assume that the move time between machines is one hour. Also, assume there are two machines

Sequence the jobs shown by using a Gantt chart. Assume that the move time between machines is one hour. Also, assume there are two machines of type A, two of type B, and two of type C. Sequence the jobs in priority order 1, 2,3, 4. Prepare a finite capacity schedule. a. What is the makespan? b. How much machine idle time is there? c. When is each job delivered compared with its due date? b. How much machine idle time is there? c. When is each job delivered compared with its due date? d. How much idle time (waiting time) is there for each job