Question: Serial activities are those that: A . Should be performed simultaneously. B . Klay's shipment of materials hit every red light and traffic jam on
Serial activities are those that:
A
Should be performed simultaneously.
B Klay's shipment of materials hit every red light and traffic jam on the way to the site. Upon arrival, half of the material was judged defective, necessitating a trip back to the supplier, and then the same arduous journey back to the site once the new materials were loaded. Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip. In the final analysis:
A
The project activity of Material Delivery had a much higher variance than anticipated.
B
The project activity of Material Delivery was pretty close to the pessimistic estimate.
C
The project activity of Material Delivery was pretty close to the optimistic estimate.
D
The project activity of Material Delivery was pretty close to the most likely estimate.
Have sequential numbers.
C
Have the same numbers.
D
Flow from one to the next in sequence.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock