Question: SET OBJECT? BY CHANGING VARIABLE CELLS? SUBJECT TO THE CONSTRAINTS ? SUBJECT TO THE CONSTRAINTS? Refer. to the FLAIR model below and the SOLVER input

Refer. to the FLAIR model below and the SOLVER input dialog box, to complete the input fields. I DATA SUMMARY Unit Profit ($1 Carpentry Labor Per Product (hrs) Painting Labor per Product (hrs) Minimum (units) 8 MODEL Production Units 10 II 12 13 Profit Contribution 14 15 Tables $32.25 3.00 3.00 0.00 Tables 1000 Tables $32.25 Chairs $15.75 4.00 2.00 0.00 Chairs Chairs $15.75 4 16 17 18 19 20 Carpentry Hours Painting Hours Min Tables Min Chairs Available or Limit N/A 3500 3000 N/A Total Profit $32,250.00 Required 3000 3000 1000 Limit or Available 3500 3000