Question: Set up a table , with columns titled Workstations, Candidates, Choice, Cumulative Time, and Idle Time. Assign work elements into workstations, one element at a
Set up a table, with columns titled "Workstations", "Candidates", "Choice", "Cumulative Time", and "Idle Time". Assign work elements into workstations, one element at a time using the longest-work-element-time rule, while keeping an eye on the "idle time" and the precedence relationships in the diagram.
| Work Element | Time (Sec) | Immediate Predecessor(s) |
|---|---|---|
| A | 23 | None |
| B | 45 | A |
| C | 24 | A |
| D | 44 | B |
| E | 31 | B |
| F | 31 | C |
| G | 29 | C |
| H | 20 | D, E |
| I | 44 | F, G |
| J | 52 | H, I |