Question: Setup Cost =$782 per setup Holding cost =$0 per unit per week Lead Time =1 Week Safety Lead Time =1 Week Scrap Allowance =5.6% Lot
Setup Cost =\$782 per setup Holding cost =\$0 per unit per week Lead Time =1 Week Safety Lead Time =1 Week Scrap Allowance =5.6\% Lot Size = LFL (Lot-for-Lot)\begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|l|}\hline Week & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 & 10 & 11 & 12\\\hline Gross Requirements & 430 & 458 & 502 & 554 & 551 & 651 & 544 & 672 & 604 & 537 & 652 & 629\\\hline Scheduled Receipts & & 486 & & & & & & & & & & \\\hline Beg. Inventory & 824 & & & & & & & & & & & \\\hline Net Requirements & & & & & & & & & & & & \\\hline Ending Inventory & & & & & & & & & & & & \\\hline Planned Order Receipts & & & & & & & & & & & & \\\hline Planned Order Releases & & & & & & & & & & & & \\\hline \end{tabular} What are your Planned Order Releases for Week 5? Round up to a whole unit!