Question: several plans, and eventually the one shown in Figure 1 was accepted by the management team. The assemble plan will run two shifts per day.

several plans, and eventually the one shown in Figure 1 was accepted by the management team.
The assemble plan will run two shifts per day. Each shift will operate for 8 hours.
The expected demand rate is 30 fans per day.
Flgure 1
\table[[Work element,Immediate Predecessor,Time (minutes)],[A,.,5],[B,*,8],[C,A,2],[D,A,4],[E,B,8],[F,C,3],[G,B, C,5],[H,F,4],[J,D, H,2],[K,G, H,7],[L,E,G,3],[M,:,5],[N,L,M,10],[P,J, K,6],[Q,L,N,8],[R,P,Q,10]]
Based on the information given in the case, answer the following questions. Show all work that you need to arrive at your answers.
e) What is the theoretical number of minimum workstations?
h) Assign work elements according to the shortest processing time rule.
 several plans, and eventually the one shown in Figure 1 was

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!