Question: several plans, and eventually the one shown in Figure 1 was accepted by the management team. The assemble plan will run two shifts per day.
several plans, and eventually the one shown in Figure was accepted by the management team.
The assemble plan will run two shifts per day. Each shift will operate for hours.
The expected demand rate is fans per day.
Flgure
tableWork element,Immediate Predecessor,Time minutesABCADAEBFCGB CFJD HKG HLEGM:NPJ KQR
Based on the information given in the case, answer the following questions. Show all work that you need to arrive at your answers.
e What is the theoretical number of minimum workstations?
h Assign work elements according to the shortest processing time rule.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
