Question: Shale Remodeling uses time and materials pricing. It is setting prices for next year using the following information: Labor rate, including fringe benefits $ 88

Shale Remodeling uses time and materials pricing. It is setting prices for next year using the following information:

Labor rate, including fringe benefits $ 88 per hour
Annual labor hours 8,200 hours
Annual materials purchase $ 1,396,250
Materials purchasing, handling, and storage $ 279,250
Overhead for depreciation, taxes, insurance, etc. $ 959,400
Target profit margin for both labor and materials 20 %

What should Shale set as rate per hour of labor hour?

Multiple Choice

  • $266.

  • $226.

  • $158.

  • $246.

  • $205.