Question: Sharon is looking to create dependencies between plans. She has identified that the deliverable of a task from one plan is required before a task

Sharon is looking to create dependencies between plans. She has identified that the deliverable of a task from one plan is required before a task in another plan can begin. Sharon decides to create a cross-project link between these two plans. Observing the image below, which of the following statements is correct?

Question 13 options:

Task 13 in this plan is very likely to be the predecessor of task 12 in another plan.

Task 13 has been deleted and is definitely not a successor or predecessor to task 12.

An error has occurred as task 13 is not visible.

Task 12 in this plan is very likely to be the predecessor of task 13 in another plan.

Sharon is looking to create dependencies between

September 2023 Task Mode 23 10 11 Finish - Predecessors Aug 15 23 8 Aug 1723 10 Aug 22 23 8,10 Aug 24 23 12 Sep 13 237 - Start Aug 923 Aug 16 23 Aug 16'23 Aug 23'23 Aug 25 '23 Zac Woodall, Hany Morcos Toby Nixon, Vikas Jain Hany Morcos, Zac Woodall Zac Woodall 12 14 15 a - Jul 18 23 Nov 7 23 - Task Name Duration Channel Sales pre 1 wk Complete book la 2 days Prepare book sale 1 wk Distribute interna 2 days Public Launch 14 days Phase Children's 81 days Gourmet Acquisition 31 days Editorial 30 days Design and 20 days Production Cover design 5 days Set pages 10 days Interior illustratio 15 days Pages review 20 days GANTT CHART Jul 18 23 Aug 30'23 Aug 30 23 Oct 10 231 Aug 30 23 Sep 26 23 555 10 III III 11 Aug 30 23 Sep 6 23 Sep 6 23 Oct 11 23 12 Sep 5 23 Sep 1923 Sep 26 23 Nov 7'23 William Flash Robin Will 14 11 1255.C:\Users 10,5 W 15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!