Question:
Sheffield Company prepared the following data in its static budget based on 112750 machine hours:
Direct Materials | $ 451000 |
Direct Labour | 221000 |
Variable Overhead | 1120000 |
Fixed Overhead | 2095000 |
Actual Results: | |
Machine Hours | 122750 hours |
Direct Materials | $477000 |
Direct Labour | 240000 |
Variable Overhead | 1152000 |
Fixed Overhead | 2107000 |
What was the difference between the actual and budgeted Direct Material costs at the actual level of activity?
$26000 unfavourable
$26000 favourable
$14000 unfavourable
$14000 favourable