Question: Shirts are made in a process with two resources. A worker in the first resource makes 7.2 shirts per hour and a worker in the

Shirts are made in a process with two resources.

Shirts are made in a process with two resources. A worker in the first resource makes 7.2 shirts per hour and a worker in the second resource makes 1.3 shirts per hour. The first resource has 2 workers and the second resource has 10 workers. Demand occurs at the rate 0.23 shirts per minute. Instruction: Round your answer to one decimal place. What is the implied utilization (%) of the first resource? %