Question: Shortening the total time for completing a project by incurring higher costs from shortening activities is called _ _ _ _ _ _ _ _
Shortening the total time for completing a project by incurring higher costs from shortening activities is called
Select answer from the options below
backward pass
leveling
crashing
normal cost
project control