Question: should be crashed first, adding to 2) Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table

should be crashed first, adding to 2) Two

should be crashed first, adding to 2) Two critical path activities are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity project cost Crash Duration Crash Cost Activity One TWO Normal Time 8 days $6,000 10 days $4,000 Normal Cost 6 days $9,000 8 days $5,000 2)