Question: show all the work Current Attempt in Progress The standard cost of Product B manufactured by Pharrell Company includes 2.3 units of direct materials at
Current Attempt in Progress The standard cost of Product B manufactured by Pharrell Company includes 2.3 units of direct materials at $6.70 per unit. During June, 26,800 units of direct materials are purchased at a cost of $6.65 per unit, and 26,800 units of direct materials are used to produce 11,500 units of Product B. (a) Compute the total materials variance and the price and quantity variances. Total materials variance > $ C. Materials price variance Materials quantity variance $