Question: show all your calculations to get full marks. Marks are allocated to information that is shown in your book not the answer. Round your answers
show all your calculations to get full marks. Marks are allocated to information that is shown in your
book not the answer. Round your answers to two decimal place ie to
The item taken from the Bill of Quantities have the following information:
Double wall made of inner wall concrete blocks and outside wall concrete bricks
The double wall is long and high.
The inner wall uses concrete blocks per square meter Allow a wastage of
The outer wall uses concrete bricks per square meter Allow a wastage of
The cost of concrete bricks is per bricks
The cost of concrete blocks is per blocks
Mortar cement sand and water mix is estimated at per square meter
There are eight workers on site bricklayers @ R day and laborers @
Rday
The cost plastering and painting the inner wall exposed side is
The production rate is estimated at per day
The construction company work hours in a day
There is a concrete mixer on site which cost R per hour.
The total overheads of the project is estimated at R per day with this item at
The profit is estimated at
You are required to calculate the following:
The material costs in
The total cost for plastering and painting the inner wall exposed surface
The Labour costs in in
The plant costs.
The overheads costs in
The Net rate in
The Gross Rate in
The total cost of the item.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock