Question: Show Attempt History Current Attempt in Progress Your answer is partially correct. Talbot Company's standard labour cost per unit of output is $22 (2 hours

Show Attempt History Current Attempt in Progress Your answer is partially correct. Talbot Company's standard labour cost per unit of output is $22 (2 hours * $11.00 per hour). During August, the company incurs 2,100 hours of direct labour at an hourly cost of $10.80 per hour in making 1.000 units of finished product. Calculate the total, price, and quantity labour variances. (Round per unit calculations to 2 decimal places, eg. 1.25 and final answers to 0 decimal places, e.g. 125.) Total labour variance $ 10800 Unfavourable Labour price variance $ 10800 Favourable Labour quantity variance $ 10800 Unfavourable
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts