Question: Show calculations - The partially completed inventory record for the table - top subassembly in Figure 1 1 . 3 5 shows gross requirements, scheduled

Show calculations - The partially completed inventory record for the table-top subassembly in Figure 11.35 shows gross requirements, scheduled receipts, lead time, and current on-hand inventory. a. Complete the last three rows of the record for an FOQ of 110 units .b. Complete the last three rows of the record by using the L4L lot-sizing rule .c. Complete the last three rows of the record by using the POQ lot-sizing rule with P =2.
FIGURE 11.35
Inventory Record for the Tabletop Subassembly
Item: M405-X Description: Tabletop subassembly
Lot Size: Lead Time: 2 weeks
Week 12345678910 Gross requirements 9085804590 Scheduled receipts 110 Projected on-hand inventory 40 Planned receipts Planned order releases
Show calculations - The partially completed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!