Question: Show me the steps to solve 2 0 . Two machining operations A ( 3 minutes per part ) and B ( 1 0 minutes

Show me the steps to solve 20. Two machining operations A (3 minutes per part) and B (10 minutes per part) are performed sequentially to manufacture a part. Machines A and B produce \(5\%\) and \(6\%\) defective items, respectively. The factory operates 8 hours each day, 5 days per week, 4.2 weeks per month. Every day each machine needs 0.30 hours for being set up. Find the machine fraction for each type (A and B) if we need to handle a demand of 1,000 items per month? Use a machine-up factor equal to \(85\%\) for each machine.