Question: Show this in Excel.. A project for improving a billing process has the followingprecedence relationships and activity times.Activity Activity Time (wks) Immediate Predecessor(s)A 3 B
Show this in Excel.. A project for improving a billing process has the followingprecedence relationships and activity times.Activity Activity Time (wks) Immediate Predecessor(s)A 3 B 11 C 7 AD 13 B, CE 10 BF 6 DG 5 EH 8 F, Ga. Draw the network diagram.b. Calculate the slack for each activity. Which activitiesare on the critical path
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts