Question: show work 17. A project is expected to create operating cash flows of $30,000 a year for three years. The initial cost of the fixed

 show work 17. A project is expected to create operating cash

show work

17. A project is expected to create operating cash flows of $30,000 a year for three years. The initial cost of the fixed assets is $75,000. These assets will be worthless at the end of the project. An additional $5,000 of net working capital will be required throughout the life of the project. What is the project's net present value if the required rate of return is 12 percent? A. $-20,157.76 $-4,386.16 $1,306.09 $5,208.11 $15,954.17