Question: show work if possible Current Attempt in Progress Using the information provided in the table, the network diagram and the project completion time - 25

show work if possible
show work if possible Current Attempt in Progress
show work if possible Current Attempt in Progress
Current Attempt in Progress Using the information provided in the table, the network diagram and the project completion time - 25 weeks, recuce the comotion time of the project by 5 weeks in the most economical www. Normal Time (weeks) Normal Cost (5) Activity Crash Time (weeks) Maximum Weeks Reduced Crash Cost (5) Crash Cost per Week (5) 380 A A 3 450 2 830 1 B 4 550 3 660 1 110 6 850 3 1.375 3 175 D 6 1.550 4 2.210 2 330 E 6 1.600 4 2,080 2 240 F 5 200 5 200 0 0 7 G 1.350 5 2 1.660 155 H 3 o H 550 550 3 0 AON network diagram B(4) E(6) A(3) C6) G(7) H(3) D(6) F(5) (if there is no amount for a box enter 0. All boxes must be filled.) Reduce A by week(s), B by week(s). C by weeks), Dby o week(s), G by week(s). E by weeks). F by week(s), H by o week(s): Total additional cost is $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!