Question: show work in excel please Below are the optimistic (a), most likely (m) and pessimistic (b) times (in days) for the activities on the critical
show work in excel please
Below are the optimistic (a), most likely (m) and pessimistic (b) times (in days) for the activities on the critical path for a large project. TASK m b A 4 15 17 00 7 12 21 C 3 ON 13 D 6 14 27 E 18 27 29 Copy data into Excel. 1. Find the project (critical path) expected time and standard deviation. 2. Find the probability of the project (critical path) being completed in 70 days. 3. How many days should be allocated to by 95% certain the project will be completed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
