Question: (SHOW YOUR COMPLETE WORK) A company has designed an energy-efficient refrigerator. It took the company 125 hours to produce the first unit. If the company

  1. (SHOW YOUR COMPLETE WORK) A company has designed an energy-efficient refrigerator. It took the company 125 hours to produce the first unit. If the company uses an 85% learning rate for this task, how long should it take the company to produce
  2. the 5th unit? [3 points]
  3. the 13th unit? [3 points]
  4. the 40th unit? [3 points]
  5. the first 5 units? [3 points]
  6. the first 13 units? [3 points]
  7. the first 40 units? [3 points]
  8. the units 6th through 13th? [6 points]

the units 14th through 40th?