Question: Shown below is a Master Schedule Record Week 1 2 3 4 5 6 7 8 Forecasted Demand 100 100 100 100 100 100 100
Shown below is a Master Schedule Record
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
| Forecasted Demand | 100 | 100 | 100 | 100 | 100 | 100 | 100 | 100 |
| Booked Orders | 100 | 90 | 85 | 80 | 72 | 66 | 72 | 56 |
| Proj Ending Inventory | 500 | 400 | 300 | 200 | 600 | 500 | 400 | 300 |
| Master Production Schedule | 0 | 0 | 0 | 0 | 500 | 0 | 0 | 0 |
| Available to Promise | 245 | ATP5 |
On Hand at the end of week 0: 600
What is the Available to Promise in Period 5 (ATP5)? Enter your aswer as a whole number