Question: Shown below is a Master Schedule Record Week 2 3 4 5 6 7 8 100 100 100 100 100 100 100 100 100 90

Shown below is a Master Schedule Record Week 2 3
Shown below is a Master Schedule Record Week 2 3 4 5 6 7 8 100 100 100 100 100 100 100 100 100 90 85 80 74 66 67 59 500 400 300 200 600 Forecasted Demand Booked Orders Proj Ending Inventory Master Production Schedule Available to Promise 500 400 300 0 0 o 500 0 o 0 245 ATP On Hand at the end of week 0: 600 What is the Available to Promise in Period 5 (ATP)? Enter your aswer as a whole number