Question: Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A

Shown below is a partially completed MPS record for ball bearings. a.

Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: Ball bearings Order Policy: 500 units Lead Time: 1 week Quantity Week on Hand: 400 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 450 450 250 350 250 250 400 350 Customer 300 350 250 250 150 150 100 100 100 50 50 orders (booked) Projected on-hand 350 0 100 inventory MPS quantity 500 0 500