Question: Shown below is a partially completed MPS record for ball bearings. Part 2 a . Develop the MPS for ball bearings. ( Enter your responses

Shown below is a partially completed MPS record for ball bearings.
Part 2
a. Develop the MPS for ball bearings. (Enter your responses as integers. A response of"0" is equivalent to being not applicable.)
Part 3Part 4
Item: Ball bearings
Order Policy: 500 units
Lead Time: 1 week
Quantity
on Hand: 400
Week
1
2
3
4
5
6
7
8
9
10
Forecast
550
350
400
450
350
400
150
250
500
350
Customer orders(booked)
300
350
250
250
150
150
50
150
100
100
Projected on-hand inventory
350
0
100
150
300
400
250
0
0
150
MPS quantity
500
0
500
500
500
500
0
0
500
500
MPS start
0
500
500
500
500
0
0
500
500
0
Available-to-
promise(ATP) inventory
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here
enter your response here

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!