Question: Significant changes in an MPS quantity several weeks into the planning horizon can: Cause inconsistencies in the MRP Reduce stockouts Increase safety stock Make the

Significant changes in an MPS quantity several weeks into the planning horizon can:
Cause inconsistencies in the MRP
Reduce stockouts
Increase safety stock
Make the MRP more accurate