Question: Simon Tech is a software company which specializes in customized programming services, particularly focusing in solutions for the banking industry. For any given project, the
Simon Tech is a software company which specializes in customized programming services, particularly focusing in solutions
for the banking industry. For any given project, the company may hire programmers in different countries of the world
through one of three setups, depending on the projects duration: under setup A a programmer is hired for two months
at $ per month; under setup B a programmer is hired for three months at $ per month; and under setup C a
programmer is hired for four months at $ per month. The longer contract periods are more expensive as usually a
freelance programmer is usually not willing to commit to a project for a long period of time.
Over the first eight months of next year, Simon has estimated the following needs for programmers. January: February:
March: April: May: June: July: and August: Simon wants to plan for staffing their projects
up until August. The companys quality control program requires each programmer to receive training at the time of
hire. The training program is required even if the programmer worked for the company in a past project. The cost of
training is estimated at $ per programmer hired, regardless of the length of the contract. Also, as a second component
of quality control, Simon requires fulltime employees to monitor the work of parttimers. These fulltime employees do
not work directly on the projects they are not part of the required number of programmers mentioned above are paid
a bonus of $ per month for their monitoring work, and each of them is in charge of monitoring a group of five or less
programmers parttimers on any given month.
Formulate a linear program algebraic formulation to help Simon determine the number of programmers to hire
each month on each setup contract type, as well as the number of full time employees dedicated to monitoring, in
order to meet the estimated needs at the minimum total cost. show all constraints for everything
Build an Excel spreadsheet model of your algebraic formulation with appropriate use of SUMPRODUCT functions and
using the good spreadsheet practices.
Run Excels builtin Solver to find the optimal solution and generate Answer and Sensitivity reports.
Answer the questions at the end of this document.
Some Questions
What is the optimal hiring plan?
What are the different costs incurred? hiring and training
Is the constraint for demand of programmers in June binding? What is the interpretation of the shadow price?
What would be the change in the optimal cost if Simon required a fulltimer to monitor four programmers or less?
What would be the change in the optimal cost if we forced the variables to take integer values? Is the cost decreasing
or increasing? Why?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock