Question: Simonson Construction Company won a contract to build a warehouse for Geller Company. The contract price was $12,800,000.Simonson estimated that the warehouse would take three

Simonson Construction Company won a contract to build a warehouse for Geller Company. The contract price was $12,800,000.Simonson estimated that the warehouse would take three years and cost $8,960,000 to complete. Actual and expected costs for the next three years were: Year 1 - $4,838,400 Year 2 - $2,867,200 and year 3 - $1,254,400.

  • Determine how much a) revenue and b) gross profit Simonson should recognize each year using the cost-to-cost method.
  • What is the major drawback of the cost-to-cost method?
  • What would be Simonson's gross profit in years 1, 2 and 3 under the completed-contract method?

Please show work

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!