Question: Simulation does not guarantee optimality. is flexible and does not require the assumptions of theoretical models. allows testing of the system without affecting the real

Simulation does not guarantee optimality. is
Simulation does not guarantee optimality. is flexible and does not require the assumptions of theoretical models. allows testing of the system without affecting the real system. All of the alternatives are correct. Question 4 (0.5 points) Activities G. P, and R are the immediate predecessors for activity W. If the earliest finish times for the three are 12, 15. and 10. then the earliest start time for W O is 10 cannot be determined. O is 15 is 12