Since the implementation of an SPC program in the foundry department in January 1990, the engineers had made one change in the foundry operations, which appear to have resulted in a 4% eduction in the scrap rate from the 1989 average rate of 28% (the standard deviation was 2%)." The table summarizes the weekly scrap rate data for the first half of 1990. Xi Xi 26.4 22.7 25.3 20.4 31.8 19.5 JOVAWN- 27.1 11 21.7 28.5 12 24 20.2 13 22.6 19.3 (a) Construct a CUSUM chart to analyze the data for the purpose of verifying the engineer's claim regarding the scrap reduction. (h =5 and k =0.25). (b) When is the process last in control? (c) What is the magnitude of the mean shift?