Question: Since the total float is 2 , which is positive we can delay the activity upto 2 days without affecting the overall completion of the
Since the total float is which is positive we can delay the activity upto days without affecting the overall completion of the project.Thus, we can conclude that optionC is the correct answer, Is not on the critical path.Option C:Is not on the critical path: CORRECT ANSWER