Question: Since the total float is 2 , which is positive we can delay the activity upto 2 days without affecting the overall completion of the

Since the total float is 2, which is positive we can delay the activity upto 2 days without affecting the overall completion of the project.Thus, we can conclude that option(C) is the correct answer, Is not on the critical path.Option (C):Is not on the critical path: CORRECT ANSWER