Question: Sinck Immediate Task Predecessors A B A D E B.CD F BD G B.CD H EFG a. Draw the network Time 2 3 4 6

Sinck Immediate Task Predecessors A B A D E B.CD
Sinck Immediate Task Predecessors A B A D E B.CD F BD G B.CD H EFG a. Draw the network Time 2 3 4 6 14 10 11 2 Earliest Start 0 2 2 2 Earliest Finish 2 3 6 8 Latest Start 0 5 7 2 Latest Finish 2 8 11 8 22 24 22 24 b. Complete the table and identity the critical path. c. What is the impact on project duration of the following changes in task times? Duration Change Task Change E increases by 2 G increases by 4 E decreases by 4 F decreases by 1