Question: sing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce. Using an 85% learning curve and a $40-per-hour labor

sing agent for Dubai Airlines, has determined
sing agent for Dubai Airlines, has determined that the second plane took 16,000 hours to produce. Using an 85% learning curve and a $40-per-hour labor charge, he wants to determine the cost of the six additional planes. Time required for the sixth unit = 12,367 hours (round your response to the nearest whole number). 202 Cost of the sixth unit = dollars (round your response to the nearest whole number). Z 20