Question: Site Process Week 8 3 . Fill the blank in following chart and complete CPM chart with given activity ( 1 5 marks )

Site Process
Week 8
3. Fill the blank in following chart and complete CPM chart with given activity (15 marks)
\table[[Item,Activity,Duration,Activity immediately following],[A,install light fixtures and plates,1,],[B,Start,0,],[C,install carpet and rubber base,3,],[D,layout for new walls,1,],[E,install electrical rough-in and inspection,3,],[F,install pre-hung frames and doors,1,],[G,project completion,0,],[H,install wall studs & suspended ceilings,2,],[I,order pre-hung doors,12,],[J,final clean up,1,],[K,paint walls and frames and doors,3,],[L,Demolition,2,],[M,install door hardware,3,],[N,board, tape and sand drywalls,10,]]
Pre-Hung Door
BCIT BLDT 1031 Week 8
34
BCIT: Construction Operations Course:
BLDT 1031
Site Process
Week 8
 Site Process Week 8 3. Fill the blank in following chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!