Question: Site Process Week 8 3 . Fill the blank in following chart and complete CPM chart with given activity ( 1 5 marks )
Site Process
Week
Fill the blank in following chart and complete CPM chart with given activity marks
tableItemActivity,Duration,Activity immediately followingAinstall light fixtures and plates,BStart,Cinstall carpet and rubber base,Dlayout for new walls,Einstall electrical roughin and inspection,Finstall prehung frames and doors,Gproject completion,Hinstall wall studs & suspended ceilings,Iorder prehung doors,Jfinal clean upKpaint walls and frames and doors,LDemolition,Minstall door hardware,Nboard, tape and sand drywalls,