Question: Situation A A construction contract contains a provision that the contractor must guarantee that a sewer system to be installed will not be subject to
Situation A
A construction contract contains a provision that the contractor must guarantee that a
sewer system to be installed will not be subject to groundwater infiltration of over
gallons per day per in diameter of pipe per mile. Upon completion of the installation,
tests reveal infiltration of gallons per day in an footrun on sixinch pipe.
Situation B
A contractor encounters rock in an urban area excavation and elects to loosen it by
blasting. Advice from experts was obtained, and the blasting operations were conducted
with great skill and care. However, cracking occurred in the plaster walls of several
houses in the immediate vicinity of the work because of the blasting.
Briefly discuss these two situations, stating whether either of them results in liability for
the contractor and, if so the type of liability involved.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock