Part 1
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
4
3
$ 2 comma 000
$ 2 comma 600
long dash
B
2
1
$ 2 comma 100
$ 2 comma 800
long dash
C
3
3
$ 500
$ 500
long dash
D
8
4
$ 2 comma 500
$ 2 comma 800
A
E
6
3
$ 900
$ 1 comma 275
B
F
3
2
$ 3 comma 200
$ 4 comma 400
C
G
4
2
$ 1 comma 400
$ 1 comma 900
D, E
Part 2
a) Based on the given information regarding the activities for the project, the project length=
13 weeks.
Part 3
b) The total cost required for completing this project on normal time=$
enter your response here.
Part 4
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
A
B
C
D
E
F
G
.
Part 5
The cost of the project based on the first activity selected for crashing will increase by $
enter your response here.
Part 6
d) The maximum weeks by which the project can be reduced by crashing=
7
8
9
10
11
12
weeks.
Part 7
Total cost of crashing the project to minimum(or maximum weeks possible)=$
enter your response here.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!