Question: Sl Code Work Package / Activity 1 1 Team Mobilization . 2 1.1 Design, Construction and Engineering Team 3 1.2 Legal & Financial Team 4

Sl

Code

Work Package / Activity

1

1

Team Mobilization.

2

1.1

Design, Construction and Engineering Team

3

1.2

Legal & Financial Team

4

1.3

Procurement & Supply Chain Team

5

1.4

Project Kickoff Meeting

6

Milestone: Team Mobilization Complete

7

Deliverable: Team Charter.

8

2

Project Approvals.

9

2.1

Finance and land leasing approvals

10

2.2

Legal and environmental approvals

11

2.3

Selecting contractor and signing contracts

12

2.4

Procurement and Supply Chain process

13

2.5

Contract finalization with suppliers

14

2.6

Phase Review

15

Milestone: Project Approvals Complete

16

Deliverable: Loan Approvals & Contracts

17

3

Construction of Dining and storage area

18

3.1

Supply of equipment and materials

19

3.2

Civil construction of Dining and storage area

20

3.3

Construction of Emergency Exit

21

3.4

Construction of Kitchen & Reception

22

3.5

Quality Check, using quality standards

23

3.6

Phase Review

24

Milestone: Construction of Restaurant area

25

Deliverable: Water heating system & Inspection Report

Please can anybody make days and predecessor of this WBS dictionary

If you can not answer the whole question please dont ruined it by answering half as users we also get limited number of chances to put questions here and the subscription is also very expensive

please see the example

 Sl Code Work Package / Activity 1 1 Team Mobilization. 2

Work Breakdown Structure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!