Question: Slack time in a network is the Select one: amount of time that you would expect it would take to complete the activity. amount of
Slack time in a network is the
Select one:
amount of time that you would expect it would take to complete the activity.
amount of time that an activity can be delayed without delaying the entire project.
amount of time that an activity would take assuming very unfavorable conditions.
shortest amount of time that could be required to complete the activity.