Question: slide #17 is below for reference 1) a task durations and dependencies table (Slide #17 in our class slides on project management) and 2) a

1) a task durations and dependencies table (Slide \#17 in our class slides on project management) and 2) a Gantt chart (Timeline chart) for the project schedule described in Slide \#20 in our class slides on project management of our textbook. Assume each task, represented by one block in the figure, takes one working day to accomplish. 3) It you start on Friday, what would be the total duration of the project if we count also the weekends and assume we have a 5 working day/week schedule? What day of the week should we start to have the shortest overall project duration for this project and why? Task durations and dependencies