Question: small engineering project has to be completed in 7 5 days maximum ( terminal time ) . The activities of the roject, their duration and

small engineering project has to be completed in 75 days maximum (terminal time). The activities of the roject, their duration and their precedencies relations are given in the following Table.
\table[[Activity,Depends on (precedence relation),Duration (days)],[A,-,12],[B,-,20],[C,-,8],[D,A (FS=3),16],[E,