Question: Small is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to

Small is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to review the status of the project. Based on the information provided. Compute:
a) the Budget at Completion (2 marks)
b) he Earned Value of the project (2 marks)
c) the actual cost (2 marks)
d) the CPI. Based on the CPI calculated what can Small conclude about the state of the project? (4 marks)
Task NameStart DateEnd DateDuration (Days)Planned ValueActual CostPercent Complete
\table[[Define,01-Apr,30-Apr,30,1,000,1,200,100%
Small is currently managing a manufacturing

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!