Question: Smallman's Garage uses standards to plan and control labor time and expense. The standard time for an engine tune - up is 3 . 2
Smallman's Garage uses standards to plan and control labor time and expense. The standard time for an engine tuneup is hours, and the standard labor rate is $ per hour. Last week, tuneups were completed. The labor efficiency variance was hours unfavorable, and the labor rate variance totaled $ favorable
Calculate the actual direct labour hourly rate paid for tuneup work last week